You are planning for cost center A, object currency DEM, in controlling area 0001 with controlling area currency USD:
Primary costs in transaction currency CHF: 450
Current exchange rate CHF : DEM :USD = 1.5 :2 : 1
The results are as follows:
Transaction currency CHF |
Object currency DEM |
CO area currency USD |
450 |
600 |
300 |
You change the exchange rate: CHF : DEM : USD = 2.5 : 3 : 2
The system recalculates the values. Following are the various possible cases:
Transaction currency CHF |
Object currency DEM |
CO area currency USD |
450 |
540 |
360 |
Transaction currency CHF |
Object currency DEM |
CO area currency USD |
500 |
600 |
400 |
Transaction currency CHF |
Object currency DEM |
CO area currency USD |
375 |
450 |
300 |