Example: Settlement of Work in Process Locate the document in its SAP Library structure

If you calculated the "change in work in process" using results analysis in the component Product Cost Accounting, this value is transferred to Financial Accounting. The value is posted to the profit center to which the production order is assigned.

FI document:

Work in process

4,000.00 to

 

to

Change in work in process

4,000.00

(PrCtr: P100)

 

Although the account "change in work in process" was not created as a cost element, since the production order does not need to be credited, the value is still transferred to Profit Center Accounting.

 