Use

Projects, such as the construction of a crane, usually involve several profit centers (for the design of the motor, for the construction of the frame, and so on). The assignment can therefore be performed in various assignable operational structures:

For more information about the structure of a project, see PS Project Management, in the R/3 Library.

By assigning project structures to a profit center, you can observe all costs and revenues posted to the structures in the corresponding profit centers. These assignments also make it possible for you to transfer work in process from projects to Profit Center Accounting.

Features

If no profit center has been entered here, project data is posted to the dummy profit center.

If no profit center has been entered here, project data is posted to the profit center in the project definition.

If an activity-assigned network activity is not assigned to a profit center, the system uses the profit center of the WBS element assigned to it.

If an activity-assigned network activity is not assigned to a profit center, the system uses the profit center of the WBS element assigned to it.

If no profit center has been entered here, project data is posted to the profit center in the network header.

Activities

To assign projects, choose Master data ® Current settings from the application menu, then choose Assignment: Projects.

You can find a detailed description of how to assign projects in the Implementation Guide (IMG) for Profit Center Accounting, under Assignments to Profit Centers.

 

 

 