The selection list enables you to display information about the requirements for the selected materials. You can then select and process individual sales documents directly from the list.
Creating a List of Sales Documents for Backorder Processing
To process backorders with a selection list, proceed as follows:
The system displays a list of the materials that meet your selection criteria. For each material, you the list provides the relevant information for each corresponding sales document (for example, the first delivery date, order quantity, confirmed quantity, and open quantity).
You can branch directly from the selection list into the individual sales documents. In addition, you can display the status, the document flow, and any changes made to the document.
Select the documents that you want to process and select from the following options:
Processing Backorders for Sales Documents
Backorder processing from the selection list always takes place by material. This means that if you select several materials in the list, the system processes each one in turn.
If you want to reschedule in order to update the sales documents before you process the backorders, note that this may adversely affect system performance. Whenever possible, carry out rescheduling in the background.
To process backorders with a selection list, proceed as follows:
This overview displays the requirements and received quantities, the quantity confirmed until now and the cumlated ATP (available-to-promise) quantity (the required and received quantities in stock still available for use) for each selected material, requirements/received date and MRP (materials requirements planning) element (such as the sales order). The requirements date generated by the sales document matches the material availability date.
Note that you can only process the MRP elements for the lines that you selected in the list for which confirmed quantities exist. The MRP elements that you can process are highlighted. Deliveries cannot be processed as backorders so the overview does not contain any confirmed quantities for them. However, the system does take the size of the delivery quantities into account when calculating the ATP quantity.
You reach the Backorder Processing: Change Confirmation screen where you can see the details of the MRP element you selected (in the Sales requirements section for sales documents). In addition to the order and item numbers and the material availability date, the following data is displayed for a sales order item:
Field |
Description |
Open quantity |
Quantity not yet delivered |
Confirmed quantity |
Quantity that has been confirmed in backorder processing |
Total confirmed quantity |
Total quantity confirmed for the sales order items (if there is more than one schedule line for the item, this is the total of all confirmed schedule lines) |
ATP quantity |
Quantity available for outwards goods movements |
In the Sales requirements section, you can process the backorders in one of the following ways:
Choose Display to branch directly to the sales document.
Additional Functions
The overview screen for requirements processing contains the following additional functions:
Variable Views Scope of Check Exception Messages MRP Elements