Procedure
Result
You see material ledger data for a material or for valuated sales order stock. The following functions are also available:
Some of these functions are relevant only for materials with single-/multi-level price determination (3), while others are also valid for materials with transaction-based price determination (2).
To display the following... |
Choose |
Price determination |
Data in other periods |
The periods in the field Period/year |
2 and 3 |
Data in other currencies |
The currency in the field Crcy type/val. |
2 and 3 |
Columns with the differences from both single-level and multilevel price determination |
The symbol Choose Display Variants |
only 3 |
To display the following data in the hierarchy... |
Choose |
Price determination |
Lines associated with a particular category (process categories, for example) |
The symbol Expand subtree |
2 and 3 |
Procurement alternatives and processes associated with the different process categories |
The symbol Expand subtree For procurement alternative Rest, you see the data directly under the process category. If there are other procurement alternatives in addition to procurement alternative Rest, you will see all procurement alternatives associated with the process category. |
only 3 |
Documents associated with the procurement alternatives or procurement processes |
The symbol Expand subtree |
only 3 |
Details on procurement alternatives or procurement processes |
The symbol Choose detail |
only 3 |
Details for the line items |
The symbol Choose detail You can call up the document item from here with a double-click |
2 and 3 |
To display the following... |
Choose |
Price determination |
Data in the material master record |
Goto ® Material Master |
2 and 3 |
Data for the standard cost estimate |
Extras ® Standard Cost Estimate... |
2 and 3 |
Other data for the material: e.g. prices, values, price control, price determination |
The symbol Additional data |
2 and 3 |
Actual BOM |
The symbol Display actual BOM |
only 3 |
Source of an error, if there is a red light in the header data |
The radio button Display Error Document |
only 3 |
Warning message, if there is a yellow light in the header data |
The radio button Display Error Document |
|
Closing document for the period displayed |
The radio button Closing Document… |
only 3 |
Closing document for the previous period |
The document line in the hierarchy under the category Beginning Inventory |
only 3 |
Sales document item |
The selection fields for the sales document item no. and the item no. under Sales Order Stock/Project Stock |
2 and 3 |
WBS element |
The selection field for the WBS element under Sales Order Stock/Project Stock |
2 and 3 |
Price history/price determination structure |
The radio button Price history/price determination structure |
2 and 3 |
You can select the following display variants:
Display variants |
Price determination |
SAP: Price history (standard) |
2 |
Actual value |
3 |
Single-level and multilevel differences |
3 |
Preliminary valuation, price and exchange rate differences |
3 |
The field Price unit is not contained in any of these display variants. You can display this through Change display variant.