Entering content frameFunction documentation Assembly Orders Locate the document in its SAP Library structure

Use

When creating a sales order the system can automatically:

The strategy group in the material master defines whether an order/network is to be created in the background.

Prerequisites

The following conditions must be fulfilled for an assembly order to be created:

Features

Exchanging Data Between Sales Order and Assembly Order

The following data is copied between the sales order and the production order:

Scheduling

The sales order contains a desired delivery date. Scheduling is carried out automatically and a material staging date is calculated. The goods receipt processing time is subtracted from the material staging date. This generates the basic finish date of the production order.

Then the production order is scheduled backwards to determine the basic start date of the production order.

For more information on assembly orders, see the SAP Library Structure link LO - Assembly Processing.

 

 

 

 

Leaving content frame