Prerequisites
You can set up backorder processing in such a way that only the requirements relevant to Shop Floor Control are displayed as missing parts. To do this, choose Settings
® Reserv. for prod.ordsDependent reservations that have not yet been committed, or for which a goods receipt has not yet been planned are displayed as missing parts. The missing quantity is displayed in the column Rec./reqd qty.
Procedure
You can assign ATP quantities to the open reservations. To do this, proceed as follows:
The system displays the details of the reservation on the date selected in the lower half of the screen.
The following data is displayed in detail:
Origin: The number of the product or assembly that requires material.
Order: Number of the source production order of the reservation.
Reqmts qty: Total quantity required for the reservation
Committed quantity: Quantity that has been committed in backorder processing.
ATP quantity: Available quantity that can be used to commit to requirements