Entering content frameProcess documentation How is the Availability Determined? Locate the document in its SAP Library structure

The availability is determined according to the ATP method (available to promise). Using this method, the system checks:

Committing Partial Quantities in Availability Checks

As a rule, the system tries to commit the entire requirements quantity of a component, providing the ATP quantity is sufficient.

Committing the entire quantity
Order quantity: 100 pieces

 

Requirements qty

ATP qty

Committed qty

Component A

200 pcs

300 pcs

200 pcs

Component B

100 pcs

40 pcs

40 pcs

Component C

50 pcs

200 pcs

50 pcs

 

If you want to ensure that the system only commits quantities that are needed in production, you can set up the commitment of partial quantities in Customizing (production scheduling profile).

In a partial commitment, only a percentage of the requirements quantity is committed. The committed quantity received by all components that are checked is determined by the component with the lowest relative committed quantity (commitment factor).

Confirming partial quantities
Order quantity: 100 pieces

 

Requirements qty

ATP qty

Committed qty

Component A

200 pcs

300 pcs

80 pcs
(40% of 200)

Component B

100 pcs

40 pcs

40 pcs
(40% of 100)

Component C

50 pcs

200 pcs

20 pcs
(40% of 50)

 

 

 

 