Entering content frameProcess documentation Example of Price Calculation Locate the document in its SAP Library structure

Sender A has the following plan and actual values:

 

Costs

Activity

Price

Plan

$100

10 hrs

$10.00/hr

Actual

$110

9 hrs

$12.22 /hr

 

The following activity input is performed:

 

Senders

Primary costs

Receivers

Activity input

Price

Plan

A

$100

B

10 hrs

$10 /hr

Actual

A

$110

B

9 hrs

$10 /hr

 

The actual activities are valuated with plan activity prices: 9 hrs X $10 /hr, resulting in allocated actual costs of $90.

 

If actual price calculation is performed, the following values result:

 

Sender credit

Sender balance

Sender revaluation

Plan

10 hrs * $10/hr =

$100

0

-

Actual

9 hrs * $10/hr =

$90

$110 - $90 = $20

9 hrs * ($12.33/hr - $10/hr)
= $20

 

If the actual sender activity of 9 hours is revalued with the difference between plan and actual prices, sender A receives a further $20 and is fully cleared. Without actual price calculation and revaluation, the residual amount of $20 (110 - (9 * 10)) remains on the sender.

 

 

 

 

 