Prerequisites
Before revaluating at actual prices, you should do the following:
Procedure
From: |
The following menu paths: |
Internal orders |
In Internal Orders, Actual postings ® Period-end closing ® Revaluation at actual prices ® Individual processing or Collective processing |
In Cost Object Controlling: |
In period-end closing for the relevant object, Revaluation at actual prices ® Individual processing or Collective processing |
Objects in the project system |
In the implementation area menu, Period-end closing ® Overheads ® Revaluation at actual prices ® Individual processing or Collective processing |
When using the cost object hierarchy, ensure that you revaluate activities that were posted to cost object nodes in a cost object hierarchy before you distribute the actual costs posted to it.
Revaluation Results
The system displays the revaluation results in a list. In addition to the selection criteria and the processing parameters, the list header contains the following data:
There is no change to the debit, if
The list itself displays the debits for the selected and revaluated objects. You can branch to the master record for each activity type. The list contains the following details:
You can display additional columns using other display variants.
Any errors that occur are recorded by the system in an error log.
You can print both the list and the error log if you select background processing.