Entering content frameFunction documentation Using Easy Cost Planning Locate the document in its SAP Library structure

Use

You use Easy Cost Planning to calculate the costs for planning objects (such as internal orders, WBS elements, internal service requests, or appropriation requests) or generally to determine costs for a specific purpose using an ad hoc cost estimate.

Integration

Cost planning is activated through the corresponding application component, such as Internal Orders (CO-OM-OPA), Project System (PS), SAP Internet Applications, Investment Management (IM), or Product Cost Planning (CO-PC-PCP).

Prerequisites

If you want to use a planning form for the cost estimate, you must have already defined the planning form in the system. For more information, see Structure linkEditing Costing Models and Assigning Attributes.

Before you can plan costs, a costing variant must have been defined in Customizing for the object to be planned. If you want to be able to see groups of costs, you must have defined cost component groups in Customizing for the application component concerned under Define Cost Component Structure.

Features

The costing screen is laid out as follows:

This graphic is explained in the accompanying text

Caution

Depending on the settings for the role to which you have been assigned, you may not be able to use all of the functions described below.

You can do the following:

Costing Structure Area

The top node is the object being planned or the ad hoc cost estimate. You cannot cost structure nodes, meaning you cannot assign them a planning form. For project structures, these are WBS elements which are not planning elements.

You can structure the object you are planning or your ad hoc cost estimate by adding new nodes (costing nodes). Select the node that you want to substructure and choose This graphic is explained in the accompanying text. Enter a description and choose This graphic is explained in the accompanying text. The node is added. The costs are calculated separately for each costing node.

To delete a costing node, select it and choose This graphic is explained in the accompanying text. Technically, this deletes a cost estimate.

You can use This graphic is explained in the accompanying text to close the cost estimate and prevent further changes from being made to it. The close is recorded in the history. You can check this in the header data. There you can undo or set the closing of a cost estimate. If you want to undo it, choose This graphic is explained in the accompanying text again.

The document flow (This graphic is explained in the accompanying text) shows for each costing item whether documents have been posted through an Execution Service for this costing item and object to be planned.

Worklist Area

If you regularly create cost estimates using Easy Cost Planning, you can load the planning forms that you use frequently into your worklist. To do this either choose This graphic is explained in the accompanying text immediately next to the node or choose This graphic is explained in the accompanying text.

You can create, insert (This graphic is explained in the accompanying text), rename, and restrict (This graphic is explained in the accompanying text) worklists, as well as modify what users can display them (change from user-specific to role-specific or all users). Use This graphic is explained in the accompanying text to call up any worklists that are in the system but have not yet been displayed. To delete worklists, choose This graphic is explained in the accompanying text. To remove subdirectories or planning forms from a worklist, choose This graphic is explained in the accompanying text. To save your worklists, choose This graphic is explained in the accompanying text in the screen area Worklists.

Item View Area

This area is used to enter, change, and display costing items. For more information, see Structure linkCreating Costing Items under the heading Features. It is not possible to make entries in the detail screen.

The item category for planning forms is J. For more information about item categories, see Structure linkMaster Data for Unit Costing. You cannot use item categories O or S in Easy Cost Planning.

Note

The item number does not necessarily reflect the position of the row in the item view. If you want to have the rows listed in order of item numbers, define a layout that sorts the rows on the item number.

For WBS elements and internal orders you can define a time frame for a costing item by entering a latest end date. The costs are distributed uniformly across the periods in the time frame you defined.

Further Item View Functions

This graphic is explained in the accompanying text

The log of the costing node currently selected is displayed.

This graphic is explained in the accompanying text

Structure linkRevaluate the costing items with the current prices.

This graphic is explained in the accompanying text

Refresh the totals and subtotals

This graphic is explained in the accompanying text

You can overwrite the price, cost element or the description for an item with the current plan and master data. To do this select the row.

Goto ® Triggered itemization on/off

If you have costed several costing nodes in one structure, all of the costing items for all costing nodes in this structure are displayed in the itemization triggered. The top node in the costing structure must be selected for this. The display can be seen in the item view.

By choosing This graphic is explained in the accompanying text you can multiply the quantities of individual costing items by a factor. The change is accepted immediately and the costing repeated.

For more information on working with this type of list display, see Structure linkSAP List Viewer.

To cost the entries or changes, choose Confirm.

Functions in the Upper Application Toolbar

Show Execution Services

After cost planning you can trigger Execution Services for some objects.

This graphic is explained in the accompanying text

Display header data

This graphic is explained in the accompanying text

You can switch between various currencies.

This graphic is explained in the accompanying text

Only displayed for ad hoc cost estimates

This graphic is explained in the accompanying text

Explains all of the symbol legends in the costing structure

This graphic is explained in the accompanying text

The error messages for all costing nodes are displayed together.

Activities

With Planning Forms

If you have selected the wrong planning form you can assign a new one. To do so, you must select the costing node. You now have the following options:

Without Planning Forms

Your role must allow you to display the item view.

Result

The results are displayed directly in the costing structure for every costing node. The costs are displayed broken down into costing items. In essence, this display corresponds both in use and structure to Structure linkvaluated BOMs in unit costing. The symbols next to the costing items specify the item category. By choosing This graphic is explained in the accompanying text for the legends you can ascertain which item category you are dealing with.

The costing items are displayed in a nonhierarchical list in the item view. This essentially corresponds to the display of the itemization. This means the respective costing items for the currently selected costing node are displayed The standard SAP system provides a variety of itemization layouts. You can adapt these to meet your individual requirements by creating your own layouts. Using various factors, you can Structure linkcalculate and delete subtotals.

Note

When currencies are translated, the system uses the exchange rate applicable on the valuation date of the cost estimate (and not the costing item, if they are different).

The values on the upper-level costing nodes are only the same as the sum of the values of the lower-level items if all costs are Structure linkrelevant to roll-up. This is specified in the cost component structure in Customizing. In addition, cost elements must be assigned to all items.

Caution

If you leave Easy Cost Planning with This graphic is explained in the accompanying text, you cost estimate is temporarily saved. The cost estimate is only saved to the database when you save the object being planned. Exception: Ad hoc cost estimates. In this case the system asks whether you want to save the data directly upon leaving Easy Cost Planning. If you choose No, the data is not saved and is lost.

You cannot save or leave the cost estimate if it contains errors. For this reason, you can only leave a cost estimate that contains errors by canceling with This graphic is explained in the accompanying text.

For internal orders, WBS elements, and ad hoc cost estimates, you can now trigger Execution Services.

See also:

Easy Cost Planning and Execution Services

 

 