Prerequisites
Define the costing variant in Customizing for Product Cost Controlling. You can specify in the costing variant whether you want the itemization to be saved.
Procedure
The screen Create Cost Estimate for Order BOM appears.
The costing variant, material, plant, and costing lot size can also be:
- Entered manually
- Transferred from the sales order item This data is transferred from the sales order item if the data has been entered in the sales order item and you do not enter any data manually here.
The system transfers the control parameters (costing dates and transfer control) from the costing variant, and costs the order BOM.
Result
The system always updates a cost component split for the order BOM cost estimate. When you save the cost estimate, you can choose whether you also want to save the itemization.
You can display the following on an order BOM cost estimate:
The costing level controls the sequence in which the materials are costed. The costing level is issued internally by the system and is inverse to the low-level code. The costing level enables cost rollup over more than one manufacturing level.
If you want to calculate the standard price for the sales order material on the basis of the order BOM cost estimate, mark the order BOM cost estimate. Do this by choosing Extras ® Mark. The system assigns the status VO (marked) to the cost estimate.
To view the cost estimate at a later time, access the Product Cost by Sales Order menu and choose Master Data/Planning ® Cost Estimate for Order BOM ® Display and enter the required data. Then choose Enter.
See also:
Standard Price with Valuated Sales Order Stock