Entering content frameConceptual documentation Floats Before and After Production Locate the document in its SAP Library structure

Since malfunctions and other disturbances in the production process can never be fully prevented, the system carries out scheduling using a float before and a float after production.

The float before production has the following two functions in the order:

The float after production is used in the order to compensate for unexpected interruptions in the production process. It prevents a delay of the scheduled finish.

The system calculates the scheduled start by adding the float before production to the basic start date. It calculates the scheduled finish by subtracting the float after production from the basic finish date (see figure).

The floats before and after production are defined in the material master record using a scheduling margin key.

This graphic is explained in the accompanying text

 

 

 

 

 