You are planning replenishments of article R100499 (chocolate) in store R151.
Article master
The following data exists for the article:
Parameter |
Value |
This means: |
RP type |
RF |
Calculate target stock during planning phase |
Replenishment run time |
3 days |
Time required between DC R300 placing PO and store R151 receiving goods |
Target range of coverage |
7 days |
Matches the delivery cycle: weekly deliveries, on Thursday mornings |
Safety stock |
10 piece |
Stock should not fall below this level. |
Maximum target stock |
500 piece |
Stock should not exceed this level. |
Minimum target stock |
Not defined |
Stock should not fall below this level. |
Current stock |
100 piece |
Stock level in store R151 on planning date |
Forecasts
A forecast is run for the next four weeks for the article. The following values are produced:
Calendar week |
20 |
21 |
22 |
23 |
Sales (in pieces) |
240 |
300 |
240 |
240 |
Replenishment Planning
You plan replenishments on the Monday evening of week 20, taking expected receipts and issues into account. Since there is a replenishment lead time of 3 days, a stock transport order is generated as a follow-on document for the replenishment run. The stock can be delivered from distribution center R300 by Thursday morning of week 20.
The planning run operates as follows (all quantities in pieces):
No such transactions are planned between Monday evening and Thursday morning. The value is therefore zero.
The period taken into account is from Monday evening of week 20 to Thursday morning of week 20. Based on 6 working days a week, 40 pieces would be sold per day in week 20. Over the total period of 2 days (Tuesday and Wednesday):
forecast sales = 2 ´ 40 = 80
Expected stock:
Expected stock = 100 + 0 - 80 = 20
The period taken into account is from Thursday morning of week 21 to Thursday morning of week 21. 40 pieces would be sold a day in week 20, 50 in week 21. Over the total period of 6 days (Thursday, Friday, Monday, Tuesday and Wednesday):
Forecast sales = 3 ´ 40 + 3 ´ 50 = 270
Target stock:
Target stock = 270 + 10 = 280
A minimum stock level was not specified. The maximum stock level of 500 is not exceeded. The result is therefore not changed.
Replenishment requirement = target stock - expected stock
= 280 - 20
= 260