Prerequisites
You have created a
flow definition. In the flow definition, you define the sequence of processing steps that you want to perform. A processing step corresponds to a single function. Examples of individual processing steps are WIP calculation, variance calculation, and settlement. A processing step sequence is defined by linking these single functions to each other in a flow definition.You have established the flow definition in the
scheduler.Process Flow
For each object, processing starts with the step that was not processed correctly.
The subsequent processing steps are then started automatically in the defined sequence.
If an object that was processed without errors in the first run of the processing step sequence is changed before the second run of the processing step sequence, these changes do not result in an automatic reprocessing of the object. If you want the object to be reprocessed, manually set the corresponding processing status.
The production order 1000000 is included with all other production orders of plant 1000 in period-end closing of Product Cost by Order. Work in process for the order is calculated as EUR 1,000 and settled to Financial Accounting (FI). All processing steps (for example, WIP calculation and settlement) of the processing step sequence were also performed without out errors.
However, not all production orders were processed without errors. In this way, for example, the production order 1000005 receives the processing status error for the processing step WIP calculation and the production order 1000010 receives the processsing status error for the processing step Settlement.
After work in process has been settled for all production orders, including production order 1000000, additional costs amounting to EUR 200 are posted to production order 1000000.
Remove the errors for the production orders 1000005 and 1000010 and reinitiate the processing step sequence. The production orders 1000005 and 1000010 are reprocessed. Production order 1000000 is not processed as it was processed without errors in the first run.
If you want to force a reprocessing of production order 1000000, you can manually set the corresponding processing status.
See also:
Schedule Manager: Worklist Schedule Manager: Monitor - Working with the Object List Processing Status of Objects and Processing Steps Processing Worklists