Entering content frameFunction documentationBackground Processing: Total Planning per Site Locate the document in its SAP Library structure

Use

Program RMMRP000 provides a purchase order proposal for all articles for a site with changes relevant to requirements planning (reorder point/ordering day reached).

In reorder point planning, the period depends on how many articles reach the reorder point at the same time.

In time-phased planning, the period depends on how the articles are distributed over the ordering days.

Usually, not all the articles in a site are planned automatically, i.e. with a purchase order proposal.

Total planning can be processed in parallel.

Prerequisites

Program RMPROG00 must run prior to requirements planning.

Activities

We recommend you run the program daily.

 

 