Entering content frameProcess documentation Material Staging via Outbound Delivery Locate the document in its SAP Library structure

Purpose

In this process you can group the components from a production order in a handling unit. You pack the components and supply the production supply area with WM/PP material staging.

For more information about WM/PP material staging, refer to the Structure link Warehouse Management component.

Prerequisites

In Customizing for Warehouse Management you have selected the delivery as the picking document (see prerequisites in Material Staging of Components with WM).

Process Flow

  1. You create a production order.
  2. For more information, refer to the Structure link Production Orders component.

  3. Create the outbound delivery.
  4. For more information, see Structure link Setting up the Interface between PP and WM Structure link and Material Staging Process Flow.

  5. You create the transfer order for the outbound delivery (see Create Transfer Order for Delivery).
  6. You confirm the removal and transfer of the transfer order (see Confirm Transfer Order).
  7. You post the goods issue to the handling unit. You have the following options:

You set which picking document you want to use as a reference, in the production scheduling profile (see prerequisites in Material Staging of Components with WM).

See also:

Picking HUs for Production

 

 

 

Leaving content frame