Entering content frameThis graphic is explained in the accompanying text Allocation: Example of Quantity Optimizing in Allocation Tables Locate the document in its SAP Library structure

The following example shows the effects of optimizing quantities for the sites and distribution centers in an allocation table item.

Sites and Sources of Supply

Ship-to party

Sources of Supply

Site R101, R102

DC R001

Site R103, R104, R105

DC R002

DC R001

Vendor 2000001

DC R002

Vendor 2000002

 

Units of Measure of the Article

The base unit of measure is piece. The following table shows the alternative units of measure and how they are used. In the example, we assume that in the article logistics data of the store and distribution center a dynamic rounding profile has been created that rounds off to order units.

Alternative unit of measure

Conversion

Unit of measure used as:

Carton

= 10 pieces

DC R001 unit of issue

Crate

= 12 pieces

DC R002 unit of issue

Small pallet

= 100 pieces

Order unit from vendor 2000001

Large pallet

= 160 pieces

Order unit from vendor 2000002

 

Quantity Optimizing for the Sites

In an allocation table item, the total quantity of 220 pieces is split up among the sites based on an allocation rule. The quantities ordered for each site are optimized, with the total quantity of the item increasing to 234 pieces.

Site

Original quantities

Optimized quantities

R101

30 PC

30 pieces = 3 boxes

R102

55 PC

60 pieces = 6 boxes

R103

10 PC

12 pieces = 1 crate

R104

60 PC

60 pieces = 5 crates

R105

65 PC

72 pieces = 6 crates

Total

220 PC

234 PC

When follow-on documents are generated for delivery to the sites (warehouse orders or deliveries), the system uses the unit of measure following optimizing. The following-on document for site R101 would therefore contain the unit of measure box.

 

Optimizing Quantities for Distribution Centers

After the system optimizes the quantities for each site, it adds up the optimized site quantities per distribution center. If DC R001 supplies 3 boxes to site R101, for example, and 6 boxes to R102, that is a total of 9 boxes (90 pieces), the system would increase the quantity ordered for the distribution center to 260 pieces. The quantities ordered for each site are optimized, with the quantity to be ordered externally increasing to 260 pieces.

DC

Site quantities in pieces

Total site quantities in pieces

Optimized quantity

R001

30 + 60

90

100 pieces = 1 small pallet

R002

12 + 60 + 72

144

160 pieces = 1 large pallet

Total

234

234

260

The difference in quantity between the order quantity (260 pieces) and the distribution center quantity (234 pieces) can be split up among the sites in the allocation table, as long as the order unit for the vendor is a multiple of the unit of issue of the distribution center.

The quantity of 10 pieces that remains with DC R001 is equal to a box and can therefore be allocated. The quantity of 16 pieces that remains with DC R002 is equal to a box plus 4 pieces. The box can be allocated. The quantity that remains (4) cannot be split up-and can and has to be put into storage in the distribution center.

 

How are Schedule Lines Managed?

If schedule lines (delivery phases) exist for a site and the item quantity changes as a result of optimizing, the system also changes the quantities per schedule line in accordance with the percentage split. If the unit of measure has changed as a result of optimizing, rounding off to whole units can lead to a change in the percentage split.

The following table shows how the stock-split for the site R102 changes for two schedule lines:

 

Delivery date
01.09.

Delivery date
01.10.

Total

Percentage split before optimizing

60%

40%

100%

Schedule line quantity after being optimized but before being rounded off

3.6 cartons

2.4 cartons

6 cartons

Schedule line quantity after being optimized and rounded off

4 cartons

2 cartons

6 cartons

Percentage split after optimizing

67%

33%

100%

 

 

Leaving content frame