Entering content frameFunction documentation Planning Order Costs on Cost Centers Locate the document in its SAP Library structure

Use

Using integrated planning of internal orders between internal orders and cost centers, you can manually plan order costs for non-planning integrated orders on the receiver cost centers. You have the following options:

- Activity-independent

- Activity-dependent

- Activity-independent

- Activity-dependent

Note

With secondary order cost planning, you can create planning records for each sender/receiver for one or for several settlement cost elements.