Entering content frameProcedure documentation Executing Activity-Independent Primary Cost Planning Locate the document in its SAP Library structure

Procedure

To plan activity-independent primary costs:

  1. Select a standard planner profile, such as SAP101 or SAPALL.

To set a standard planner profile, choose:

  1. Choose Planning ® Cost and activity inputs ® Change

Choose Change to enter new primary costs or change existing ones. There you can enter the plan total per cost element, and by specifying a standard distribution key or a user-defined one (see Customizing for Cost Center Accounting under Planning ® Planning Aids ® Create Distribution Key) you can distribute it to the plan periods. In the period screen you can also distribute the period values manually.

For more information about planning and changing planning screens, see Executing Manual Planning and Techniques for Supporting Manual Planning

 

 

Leaving content frame