Calculate WIP for Manufacturing Orders in Engineer-to-Order

Definition

Inengineer-to-order environments with a nonvaluated project stock, selecting this indicator has the following effects:

Use

This indicator is only relevant in engineer-to-order environments if you are using a nonvaluated project stock. It is of particular importance if you are engaging in cross-company production.

For the system to interpret the indicator, a results analysis key must be specified on the WBS element to which the order is assigned, or on the billing element above that WBS element. If this requirement is not met,results analysis data for the order is always calculated regardless of whether the indicator is selected.

If the indicator is selected, the determining factor is whether or not there is a results analysis key in the order assigned to the WBS element.

If the indicator is not selected, results analysis data for the orders is calculated through results analysis for the WBS element.

If you are engaging in cross-company production in an engineer-to-order environment with a nonvaluated project stock, you should select this indicator. In this case, specify a results analysis key in the orders assigned to the WBS element. You can define this results analysis key as a separate default value for each order type (see also: Define Default Values for Order Types (PP und CO) ).

Dependencies

The indicator Calculate WIP for Internal and Service Orders w/o Revenue is only relevant if the internal and service orders without revenue are not assigned to a WBS element. If the internal and service orders without revenue are assigned to a WBS element, the setting of the Orders in engineer-to-order indicator takes precedence.