Check Valuation
Variants for Product Cost Collectors
In this step you check thevaluation variants
for Product Cost by Period.
- The valuation variant for the preliminary
costing of the product cost collector is used to determine the
following:
- Which price is used to valuate materials,
external activites and subcontracting and which activity price is used to
valuate activity types and business processes
- Which costing sheet is used for preliminary
costing
- The valuation variant for simultaneous costing
is used to determine the following:
- What activity price is used to valuate the
actual activity type and business process postings
- Which costing sheet in the product cost
collector is defaulted
This costing sheet
is used for overhead calculation in period-end closing.
Strategies for
material valuation or price determination for external processing and
subcontracting are not included in simultaneous costing and final
costing.
To be able to use the valuation variant, you
must assign it to a costing variant.
Standard
Settings
- The standard system contains a number of
predefined valuation variants. If necessary, you can change these valuation
variants to meet your requirements by changing the standard strategy
sequences.
The following default valuation variants exist
in the standard costing variants for Product Cost by Period:
- 001 - Plan Valuation Material
This valuation
variant for the preliminary costing of the product cost collector is specified
in the SAP standard costing variant PREM (Preliminary Costing, Cost
Collectors).
- 007 - Production Order, Actual
This valuation
variant for the simultaneous costing of product cost collectors is specified
in the SAP standard costing variant PPP3.
Actions
1. Enter an
alphanumeric key and a name for the new valuation variant.
2. Specify the
relevant valuation strategies.
3. Enter a
costing sheet.
4. Assign the
valuation variant to a costing variant.
Note
If you want to use different valuation
strategies or different overhead rates in plants that belong to the same
company code, you can define plant-specific valuation variants by assigning a
valuation variant to a plant. Choose the push button Valuation
variant/plant. If you don't do this, the valuation variants