The 'Update planned records' function only relates to the derivative financial instruments cap, floor, swap and FRA (product categories 610, 620, 630).
You can determine interest payment amounts, which result from derivative financial instruments, using a variable index (reference interest rate), such as the Libor.
When you create a derivatives transaction (such as a swap) in the 'Derivatives' application, flows are generated for the variable interest, which only describe the payment date. Since the payment amount depends on the future trend of the reference interest rate, this can only be added later. To do this in the system, you use the 'interest rate adjustment' function.
In the SAP System, you can transfer payments to Cash Management (CM) in order to reflect a correct liquidity status. This means that you can only estimate the interest amount for payments, which result from reference interest rates, if the interest rates have not been adjusted. Go to the Cash Management update function by choosing Back Office -> Update planned records from the menu.
You can use the company code, transaction number, and product category as selection criteria. If you have selected the 'test run' indicator, the database is not updated. The selection date controls the date for which the reference interest rates are valid. This is usually set to the current date.
The reference interest rate values are stored in the system so that they can be used for the most varied objects (such as floaters and swap transactions). The derivatives application also includes a 'manual interest rate adjustment' function, which enables you to assign values to a single transaction for the reference interest rates used for this transaction. These individual values are not generally available. If, when you update the planned records, you want to use these values in addition to the reference interest rate values which are generally available, you have to set the 'note manual interest adjustment rate' indicator. The system then makes all the reference interest rate values that were entered manually available to all OTC interest rate instruments along with their validity dates.
If you enter a date when you select your data, the system chooses from all the values available in the system, one that is valid on this date. If you do not enter a date, it uses the most recent value defined. This reference interest rate value is the one which is assumed as valid for all future dates.
The data is listed according to the
Points 1, 2, 5, 6, and 7 are self-explanatory.
The interest column (point 3) enables you to drill down to the interest value (including the reference) used for the update. If an error occurs, this means that although the reference interest rate is used in one or several transactions, the system did not find a value for this reference.
When you double-click the updates column (point 4), you can see the information that is updated to Cash Management, if the test run indicator is not set.
The CM update column (point 8) tells you whether the CM update was successful. If errors occur here, check the Customizing that controls the CM update.
In addition to updating the planned records in the way described above, (which can be done at any time), you can also update the planned records when you process transactions by using the 'create', 'change', 'give notice', 'reverse', and 'interest rate adjustment' functions. The calculation logic is the same as that of the 'update planned records' function, which you achieve by setting the 'note manual interest rate adjustment' indicator. The system uses the transaction processing date as the date.
None
None
Daily batch run
You enter the planning level at product type level in Customizing in order to assign a planning level in CM to the business activity.
You must also make sure when defining the flow types for the interest flows that they are indicated as 'Relevant to CM'. Otherwise, they are assigned a cash management block.