Processing with an External Company as Work Center
Purpose
For an external company that you regularly hire for the same tasks, you can create a special
work center.This can be advisable if the external company is not situated near to your company, and they process a large number of orders for you.
Prerequisites
You configure a cost center for each external company individually or for all the external companies collectively.
In Controlling (CO), you configure a CO activity type and a price, which reflects the conditions of the purchase order, for the cost center of the external company.
For the external company, you create a work center that is linked with the cost center and the CO activity type.
Since this form of external processing is identical with internal processing during order processing, you assign a control key for internal processing to the operations to be processed externally. In the standard system, this control key is PM01.
Process Flow
The costs are first collected on the order and then settled to the receiver specified in the settlement rule.