Create Activity Items for Activity Item Custom Fields

Context

In this task the Buyer creates individual activity items for each custom field described in the table "Custom Field List: Buyer-Side", as described in Create Custom Fields for Activity Item Module. Each field gets its own activity item with the related custom field attached. During processing, each time an activity item is completed on the supplier system, that date is updated in the activity item in SAP Fieldglass.

If you want to use alerts and timeline planning, you can link each activity item to require its completion n number of days after the previous one. If a date is missed, it generates alerts to Number them so they list in sequence order. Manifest is sequence 1.

In addition, ensure all activity items are linked to the appropriate worker roles (equipment types) and suppliers, and all are visible to suppliers.

Procedure

  1. Log into the Buyer company, and on the Administration Menu under Workflow, choose Activity Item.
  2. Choose New.

    The What Type of Activity Item Would You Like? dialog box opens (step 1).

  3. Choose the Other tile.

    The Other dialog box opens.

  4. Choose the Complete Custom Fields tile.

    The Add New Activity Item page opens.

  5. Complete the following details:
    1. In the Code field, enter a code name for the manifest, for example, MF.
    2. In the Action field, enter Manifest.
    3. Enter an optional Description.
    4. In the Actor list, choose (Supplier Account) (required).
    5. Under Usage leave the default value No selected.
    6. Completion Based On Prerequisite allows you to use alerts and timeline planning to link activity items that require completion based on a prerequisite. If the timelines aren’t completed on time, the customer receives notification alerts.

      To enable this optional feature, choose Yes, and under Prerequisite, click the Select button and choose a prerequisite value. Then configure all the remaining options.

      The best practice is to create completion values according to your timelines to ensure that everything gets completed on time. For example, the equipment arrived at the dock 2 days ago, but no one confirmed it’s on a barge, or the equipment stopped being used, or the SOW was finished 2 days ago, but nobody's put it back on a barge and so you're still being charged for it.

    7. In the Manage SOW Worker Activity Items On option, the default value is Create. Change to Create and Revise, if needed.
    8. In the Frequency option, the default value is Once. Change to Recurring, if applicable.
    9. In the When will this be due? list, choose an option.
    10. In the Send Work Items option, enter a value for the number of working days before the due date to send the work items.
    11. In the Escalate option, enter a value for the number of working days after the due date to escalate the activity item.
    12. In the Cancel Activity Item option, enter a value for the number of calendar days after worker close to cancel the activity item.
  6. At the bottom of the page, choose + Add Custom Fields.

    The Add Checklist Item Custom Fields dialog box opens.

  7. Select the check box next to each of the Activity custom fields you created in Create Custom Fields for Activity Item Module.
  8. Choose Add Selected to add the custom fields to the activity item.
  9. On the Add New Activity Item page, choose Add to add the new activity item.
  10. Repeat steps 2–9 for each custom field name you created (as referenced in step 7). Be sure to enter them in the sequence listed.

    When you display the details of each "Other" type activity item, its custom field displays at the bottom of the page.