Displaying the Test Dates in the Testing ScheduleWhen the system has scheduled the test dates for the stability study, you can view these dates in the testing schedule.
Note
The procedure below describes how to display a testing schedule using a transaction in the key functional area
Asset Life-Cycle Management
. In this area, the
testing schedule
is referred to as a
maintenance plan
. These objects are identical and the terms are synonymous.
You have defined a start date for the stability study, which in turn has triggered the scheduling of test dates for the study.
From the
SAP Easy Access
menu, choose
.
The initial screen for displaying a maintenance plan (testing schedule) appears.
On the initial screen, enter the key of the maintenance plan you want to display and then choose
Enter
. If necessary, use the possible entries help to select a maintenance plan.
The screen for displaying the data in the maintenance plan appears.
You can display all scheduled test dates or the test dates for specific items only, as described below:
In the maintenance plan header |
Choose the
or Choose |
At the item level of the maintenance plan |
In the lower part of the screen, select a maintenance plan item and then choose the
|