Copying an Organizational Structure On the
Compensation Management
screen, choose
The
Create Budget Structure: Initial Screen
appears
Choose
On the Generate Budget Structure screen, enter the name of the organizational unit that you want to copy.
Select a budget type and a budget period for the budget structure that you want to create.
Enter data as required in the
Options
section
Set the
Use organizational unit's relationship period
indicator if you want the system to take relationship period between the root organizational unit and the subordinate organizational unit into consideration.
Do not set this indicator if you want the system to use the period in which both the organizational unit and the corresponding budget unit exist.
Example
Object |
Validity Period |
Org. unit O1 |
01.01.1998 - 01.10.1998 |
Org. unit O2 |
01.03.1998 - 01.11.1998 |
Relationship O1 - O2 |
01.05.1998 - 01.07.1998 |
Budget unit BU1 |
01.01.1998 - 31.12.1998 |
Budget unit BU2 |
01.01.1998 - 31.12.1998 |
Relationship BU1 - BU2 |
01.01.1998 - 31.12.1998 |
If the indicator is set, the relationships between the budget units and the organizational units will have the following validity periods:
Relationship |
Validity Period |
BU1 - O1 |
01.02.1998 - 01.10.1998 |
BU2 - O2 |
01.05.1998 - 01.07.1998 |
If the indicator is not set, the relationships between the budget units and the organizational units will have the following validity periods:
Relationship |
Validity Period |
BU1 - O1 |
01.02.1998 - 01.10.1998 |
BU2 - O2 |
01.03.1998 - 01.11.1998 |
Choose
The system copies the organizational structure and creates the corresponding budget structure. The system automatically assigns the organizational units to the corresponding budget units. The system gives the budget units the same name as the organizational units that they finance.