Estimation of Planned CostsSeveral different types of costs can be incurred when executing an order. To obtain an overview of the likely costs before actually performing the work, you can use the system to calculate automatically and then display the estimated costs for the work planned.
Planned costs are only displayed for an order if you have assigned a control key to the individual operations in the order, which includes them in the costing process. Operations that do not have an appropriate control key assigned to them are not considered when the costs are estimated.
Note
If scheduled material components are not to be included in the cost estimation, you must delete the RelevCosting
indicator on the general data screen for the individual components.
The work center specified in the operation is linked to a cost center. The valid activity type is also entered in this link. The valid price and cost element are contained in the activity type.
Generally, the system determines the costs, which arise for the order operation, based on the following formula:
Cost of work performed = Working hours x Price in the activity type
The costs are then displayed in the cost overview in the order at cost element level.
Example
Work center | Mechanics 1 |
|---|---|
Work | 3 hours |
Cost center | 511 |
Activity type | Maintenance of machines |
Cost Element | 452000 (maintenance costs for machines) |
Rate | $ 100 |
Assigned costs in cost overview | Maintenance costs for machines: $ 300 |
The following applies for services:
The system performs a cost element determination for each service that you enter for an operation. If you enter different services, for which the system determines different cost elements, then the costs for these services are listed separately in the cost overview.
For more information about services, see External Services Management (MM-SRV).
The planned costs for an order can be estimated in the following ways:
Automatically when the order is being saved
After you have made all the entries in the order header and in the order operations, the system automatically determines the costs for the planned work from the order data whilst the order is being saved.
Specifically by calling up the Determine costs
function
After you have made all the entries in the order header and in the order operations, choose on the header data screen for the order. The system determines the costs for the work planned from the order data.
Note
The following applies to both types of cost estimation:
If the system is unable to determine the costs, you can display the reason in a log. To do this, choose .
For more information about how you can display the results of the planned costs estimate, see Displaying Costs.