Enable Cost Center Upload Connector

The Cost Center Upload connector is required to upload to and manage data in maintanence orders.

Context

This task can be performed by the Buyer's Admin.

Procedure

  1. On the Configuration Manager Self-Service Dashboard, choose the Connectors tile.
  2. On the Connector List page, choose the Connector Catalog tab.
  3. Locate the 'Cost Center Upload' connector version 'API-A-V1.0', and click the connector name hyperlink.
  4. On the connector Integration page, choose Edit (or if the connector is disabled, choose Enable to activate it).

    The Connector Setup page opens in the setup wizard.

  5. Follow the instructions below and in the setup wizard to configure the connector, choosing Next to advance through the setup pages.
    1. In the Connector Name field, enter a custom name, for example Maintence Order Upload - variant 1.

    2. In the Upload Data Format option, choose JSON.

    3. In the Pre-Processor list, choose insite.partner.preprocessor.JsonToCsvPreProcessor.preProcess.

    4. In the Customize step under Upload Column Transform, choose + Add Native Field to add the following native field:

      Upload Column Mappings

      Standard Column Name

      File Column Name

      Default Value

      Cost Center Code

      MaintenanceOrder

       

      Cost Center Name

      MaintenanceOrderDesc

       

      Legal Entity

      CompanyCode

       

      Account Category

       

      MaintenanceOrder

      Currency

       

      ALL

      Include All Expense Flag

       

      Yes

      Include All Task Flag

       

      Yes

      Reason

       

      Closed by integration

    5. Choose Next.

    6. In the Connectivity step under Transfer Method, choose Subscription.

  6. To save the subscription, choose Save.
  7. Choose Exit Wizard.
  8. To test the connector upload, on the Self-Service Dashboard, choose the Integration Subscriptions tile. On the Subscription List page, run the MDI_MAINTENANCEORDER subscription to enable data polling using the end point and cost center variant you created, and then choose Run Now to test and enable the sequence to run.
  9. Verify the connector activity for cost centers processed in the Integration Audit Trail.

Next Steps

To complete the Maintenance Order Configuration see Add Maintenance Order End Points and Add Maintenance Order Subscription