Special Settings in the Control Cycle You usually use control cycles as master data for controlling the replenishment of a certain material at supply segment level.
To be able to use automatic supply-to-production, you usually create the control cycles for your supply areas for automatic, summarized JIT calls .
Note
In the supply-to-production table, you can also work with control cycles that are based on manually created summarized JIT calls . Here, however, you must note that these control cycles or supply segments are not included in an automatic planning run.
If you want to work with manually-created, summarized JIT calls, you must have set the indicator
Manual Summarized JIT Calls in Change Mode
in the global settings, in the
Planning
tab page under
Further Settings
.
For more information, see also Creating Control Cycles for Automatic Summarized JIT Calls .
The following parameters in the control cycles are particularly important for automatic supply-to-production:
Quantity per call item and number of load carriers
These quantities determine the rounding logic. Rounding is controlled as follows:
If a packing instruction is saved in the control cycle and a functional use of this packing instruction is defined in the replenishment strategy, the cumulated target quantity of the packing instruction is used as the rounding quantity.
If no functional use of the packing instruction has been defined, the
Quantity per call item
saved in the control cycle is used as the rounding quantity.
If you have defined a
Number of load
carriers in the control cycle, the system always rounds up to at least the
Number of load carriers * Rounding quantity
.
If, in the packing instruction, you have defined that only one load carrier per call item is to be staged then, as well as rounding the quantities, the system also splits the replenishment proposals so that a replenishment proposal does not exceed the maximum quantity of a load carrier. In this case, the rounding no longer refers to individual replenishment proposals but to all the requested replenishment proposals for a specific point in time.
For more information, see also Creating Replenishment Proposals .
Planning horizon and minimum stock The planning horizon and minimum stock are used to control the missing quantities calculation. For more information, see also Missing Quantities Calculation .
Lot-sizing procedure
The lot-sizing procedure determines how the individual replenishment elements are grouped.
Lot-for-lot order quantity
The replenishment proposals are not grouped when using this lot-sizing procedure. You typically use this procedure for demand-driven, automatic supply-to-production combined with a rounding logic. This rounding logic triggers a grouping by quantity criteria which prevents the replenishment proposals from becoming too fragmented.
Lot size “One lot”
The system groups all the calculated replenishment proposals when using this lot-sizing procedure.
For more information, see also Creating Replenishment Proposals .
Scheduling type
You have the following options:
Requirements date = first material shortage date
Immediate requirement including replenishment lead time according to control cycle
If you do not define the scheduling type in the control cycle, the system only creates immediate requirements. For more information, see also Creating Replenishment Proposals and General Prerequisites .