Changing a Document and Completing an ECOTo complete a document change, the following must apply:
The current status of the
change master record
(object management record for the document) must support the
Complete change
system status as the next status.
The current status of the
document
must support a follow-up status that has the
Complete for
engineering change management
indicator set for it.
Change the document (
– For example, change an original application file and check it into a vault.
– Set the document status that has the
Complete for engineering change
management
indicator set for it.
The system checks the object management record of the document in the allocated change master record. If all the requirements have been fulfilled, the system automatically changes the change master record (the object management record for the document receives the
Complete change
system status).
Edit the change master record.
After changing an object, you must set the system status of the object to
Complete change.
You only need to take this step for those objects that have already been assigned the system status
Change possible
.
You can only complete the engineering change order once the system status
Complete change
has been set for all objects.
Exception for documents:
The processing status
Complete
is not set in the change master record for documents.
Once all objects affected by the change have the
Complete change
status, an additional check can be performed. The business transaction
Release change
is defined for this purpose.
Change the system status of the change objects and the change master to
Release change
and
Release order
respectively.