Budget ValuesThe drilldown reports listed below are used for analyzing the budget values of an investment program:
Comparison of plan and budget values in an investment program
For each program position, the system shows the plan and budget values, and the difference between the two. The comparison is made for the overall values and for annual values.
Distribution of the overall budget in the investment program
For each program position, the system shows the total distributed budget, the budget that was distributed to lower positions in the hierarchy, and the budget that is still distributable. The report shows these values, separately by approval period, for
The sum of the overall values (balance forward, current and forecast)
The overall value budgeted in the current year (current)
The overall value carried forward from previous years (balance forward)
The overall value predicted in the forecast (forecast)
Distribution of the annual budget in the investment program
This drilldown report corresponds to the one above. However, it shows the annual values rather than the overall values.
For more information see Fiscal Year Change .
Overall budget and annual budget in investment program
For each program position, the system shows the overall value across from the annual values.
Budget updates
For each program position, the system shows the original budget, supplements and returns, and the resulting current budget. These values are displayed both for overall values and annually.
Budget by reason for investment
Here the system shows the overall and annual budget of all end nodes (the positions in the hierarchy with no positions subordinate to them) in an investment program, broken down by the reason for the investment. (Possible investment reasons include replacement investment, rationalization, expansion, environmental protection). The first screen of the drilldown report shows the totals of all these budgets by company code.
Budget distribution from the investment program to the investment measures belonging to it
The report shows, per program position, the budget value of the position, the budget distributed to the individual measures belonging to the position, the budget that can still be distributed, the budget already used in the form of funds committed at the level of the individual measures. This comparison can be made for overall values and for annual values.
Overall budget and annual budget of the investment measures belonging to an investment program (totaled by program position).
Budget distribution from the investment program to its investment measures, broken down by standard budget category (refer to Budget Categories ).