Replacement by a Measure for ImplementationWhen an appropriation request is ultimately approved, another system object, referred to as a measure, has to be created. The measure is required in order for you to continue to manage the investment in the system. You can create a measure for an appropriation request directly from master data maintenance for the appropriation request. Below are the system objects that can act as measures:
Internal orders or maintenance orders
WBS elements
Note
An appropriation request can have an unlimited number of measures. However, a measure can be related to only one appropriation request.
The project profile or order type to be used can be entered in one of two places. Either you enter it in the appropriation request type in Customizing, or you enter it when you create the measure.
To generate maintenance orders from appropriation requests, you first have to specify a PM order type as relevant for investment measures. You make this setting in Customizing for
Plant Maintenance and Customer Service.
Choose
. You then enter the PM order type in the appropriation request type or in the master data of an appropriation request.
The system stores the assignment of the appropriation request to the measure. You can display the mutual dependencies of the two objects in their master data.
Manually Editing the Assignment
You can edit the assignment between an appropriation request and a measure even after the measure has been created.
Number Assignment
You control number assignment for creating measures for the appropriation request in the appropriation request type. For more information see Number Assignment .
Copying of Master Data Information
When you create a measure for an appropriation request, the system copies certain master data information from the request to the measure. The master data copied is listed below:
Description
Planned implementation start date
Depreciation simulation data
Object currency
Controlling area
Company code
Company
Functional location
Plant
Business area
Profit center
Cost center
Scale
Environmental indicator
Caution
Percentage distribution to several environmental indicators is not possible on the measure. The system assigns the measure the environmental indicator that has the largest percentage in the appropriation request.
Create Project with Template
When creating projects from within appropriation requests, you can use operative or standard work breakdown structures as templates.
Caution
Any networks assigned to the template are not copied.
The data of the appropriation request is copied as follows:
Plan values and depreciation simulation data |
First top WBS (work breakdown structure) element |
Assignment to investment program |
All top WBS elements (when measure is replaced) |
Short and long text |
All top WBS elements |
Master Data |
All WBS elements, if the data was maintained on the appropriation request. Otherwise the data of the reference is retained. |
Copying of Assignment to Investment Program
The system automatically assigns the measure to the investment program position, to which the appropriation request was assigned.
Copying Plan Values
Along with the master data, the system copies planned costs from the appropriation request to the measure.
There are two ways in which the copying of plan values can be triggered:
Automatically, when the measure is created from within master data maintenance of the appropriation request
By choosing the
Adopt plan values
function on the
Measures/assets
tab page.
Which Variant Supplies the Plan Values to Be Copied?
An appropriation request can have several variants (refer to Appropriation Request Variants ). All variants have plan values, but only one can supply the plan values to the measure. There are two possible scenarios:
One
variant has
approved
or
for approval
status.
In this case, the system automatically copies the plan values of this variant to the measure. (Only one variant can have either of these statuses.)
No
variant has
approved
or
for approval
status.
In this case, the system displays a dialog box. You have to choose the variant to be used. (The dialog box displays all variants that have not been rejected.)
Copy to Which Plan Version?
Plan values of measures are managed in plan versions, which are universally valid (refer to Versions for Planning ). Appropriation request variants are also assigned to these plan versions. When you copy plan values to one of these plan versions, there are several possible situations that can occur:
The
Replace with measure
indicator is set in the Customizing definition of the appropriation request type. Then the system copies the plan values of the variant to the version to which the variant itself is assigned. (This does not apply to costed values, see below.) If the variant is assigned to several versions, the system displays a dialog box in which you can select from the assigned versions.
The
Replace with measure
indicator is
not
set in Customizing, or the variant is
not
assigned to any version. Then the system automatically transfers the plan values to version 0.
Copying Costed Values
Costed values (values from a cost estimate) can only be copied when you create a measure from within the appropriation request. It is not possible to copy the cost estimate at a later point in time. The system copies either the plan values or the cost estimate to the measure:
If a cost estimate is entered on the variant, the system copies this cost estimate to the measure. After that, no further copying of plan values is possible.
Note
The cost estimate is not copied to the measure unless you set the
Copy cost estimate
indicator in the appropriation request type. If this indicator is
not
set, you can make numerous cost estimates, and copy the plan values they supply as often as you wish.
If the cost estimate in the variant is structured hierarchically, you can select a subtree of the cost estimate for transfer, rather than the complete cost estimate. Each (sub)cost estimate can only be copied once to a measure.
Caution
The entire cost estimate is locked after the transfer of the first cost estimate subtree, because the system may not be able to prevent multiple transfer of plan values if there are later changes to the structure. However, you can unlock the cost estimate manually.
If there is no cost estimate entered on the variant, the system copies the plan values to the measure. After that, you can continue to copy plan values, but only as long as you do not enter a cost estimate for the variant.
The system calculate costs on the measure using the functions for revaluating the cost estimate. The system revaluates the cost estimate based on the Customizing settings for Easy Cost Planning of the measure. The overall values of the two cost estimates can differ due to differences in Customizing.
Copying Costed Values
The system determines the variant, from which plan values are copied into the measure, independently of whether or not a cost estimate exists (see above).
Cost Estimate and Plan Version
For internal orders, the system does not copy the cost estimate to a special plan version. This applies even if the appropriation request type specifies that the appropriation request is replaced by the measure.
For WBS elements, the system copies the cost estimate to plan version 0. However, you can define a separate plan version in Customizing for the
Project System
for Easy Cost Planning.