Estimates

Use

Using this method involves making a subjective assessment of the project degree of completion. The method is schedule-based. This measuring technique is based on scheduling.

You use this technique when no other, objective method is available. The work package duration for this technique should be more than three months.

Prerequisite

  • You must manually maintain a plan or actual percentage of completion (POC) for the WBS element/activity for each period. The system prescribes the periods on the basis of the dates maintained.

The following table gives you an overview of the menu paths to choose so that you can maintain data you need for your estimates:

Object

Maintain estimate data by choosing...

Projects in structure planning

Start of the navigation path Details Next navigation step General, Next navigation step then Progress tab page, then choose Estimated value End of the navigation path

Projects in the project planning board

Start of the navigation path Details Next navigation step Detailed information on object, Next navigation step then Progress tab page, then choose Estimated value End of the navigation path

WBS elements

Start of the navigation path Details Next navigation step General, Next navigation step then Progress tab page, then choose Estimated value End of the navigation path

Activity or activity elements

Start of the navigation path Details Next navigation step Activity/element Next navigation step General, Next navigation step then Progress tab page, then choose Estimated value End of the navigation path

In addition, you can also enter a measurement method for estimates and a maximum percentage of completion in Project System customizing.

A maximum POC prevents an overestimate of completion such as occurs when tasks are "almost finished" (also called the "90% syndrome"). As long as the task has not been completed, that is, no actual finish date has been entered, the system will not allow you to have an actual POC that is higher than the maximum POC.

Note Note

We recommend a maximum POC of 80% for the actual POC estimate.

End of the note.

Features

In this measurement method, the system adopts the percentage entered manually as the POC for the specified period.

Note Note

You always enter the cumulative estimate. The values are not regarded as additive.

End of the note.

Example

Plan Dates

Estimated Values

Planned POC

05.99

10%

10%

06.99

30%

30%

07.99

100%

100%