Executing the Milestone Trend Analysis You have to have
created milestones
for the WBS elements and/or activities and set the
Trend analysis
indicator in the
Usage
section of the detail screen.
You must have created project versions in the information system for the required report dates.
To do this, in the Project Information System choose
Now choose
On the dialog screen enter the version key, the version group, and if required a description of the version.
For the data to be used in milestone trend analysis, you have to set the
MTA relevant
indicator in this dialog box. This indicator is set as a default, since in general it does adversely affect performance.
To access the
milestone trend analysis
, choose
Logistics
or
A selection screen appears, in which you limit which milestones are displayed by selecting
projects
,
WBS elements
,
networks
and/or
activities
.
You can determine whether basic dates or forecast dates are used for the milestone dates . You can also change which set of dates is used in the MTA.
You use the
Use current data too
indicator to determine whether the dates from the operative project are used or whether only data from the project version is evaluated.
Choose
.
The MTA chart appears in which the dates of the selected milestones are plotted against the report dates.
By double-clicking individual graphical elements, you can open dialog boxes for changing these elements. For instance if you double-click the axes you can change the axis text, scaling, and so on, or by double-clicking the curves the formatting of the data. For general information about this kind of graphic, refer to Chart OCX Presentation Graphics
If you want to see the table instead of the graphic, choose
The table with the milestone dates on the report dates appears.
For here you can go to to the detail screen of a selected milestone by choosing
In both the graphic and the table you can restrict the number of milestones or report dates that are displayed by choosing
Note
You can also access MTA in the project planning board. To do this, select the relevant WBS elements and choose .