Cost ProportionalityThis measurement technique is suitable for work packages where costs and services have a constant relationship.
Costs must have been planned in the object, or actual costs posted to it, by period.
Note
The system does not take account of costs from hierarchy planning in the WBS element.
The system determines the percentage of completion (POC) for a period from the ratio of planned or actual costs to the overall planned costs. The system determines the planned or actual POC as follows:
BCWS = Planned costs/overall costs * 100
Actual EV = Actual costs/overall costs * 100
The planned costs are the cumulative planned costs up to the time of the calculation. The overall planned costs are the cumulative planned costs over the duration of the work package. You use the progress version to stipulate which cost plan the system uses.
A work package has overall costs of $100,000.
The table shows how the POC is determined with reference to the overall costs.
Period |
1 |
2 |
3 |
Planned costs |
10,000 |
50,000 |
100,000 |
Planned POC |
10% |
50% |
100% |
Actual costs |
5,000 |
30,000 |
90,000 |
Actual POC |
5% |
30% |
90% |