Calculating Your Project’s ProgressThe system uses this function to calculate the percentage of completion (POC) and earned value. You can run the progress calculation in individual or collective processing any time you like. You can also run the calculation more than once - for example, if the plan changes.
You must make the settings necessary for the progress calculation in the Project System IMG.
For more information, see Progress Analysis .
If you want to run the progress calculation in collective processing, you require a selection variant. You can create the selection variant in the initial screen for the collective agreement.
Choose
Logistics
or
Enter the controlling area, as required.
This brings you to the
Project Progress
screen
.
Enter whichever of the following you require:
Project definition
WBS Element
Network
Note
Set the
Include orders
indicator if you want networks and orders assigned to the project or WBS element to be included in the selection.
Enter the following parameters:
Progress version
You use the progress version to stipulate various control parameters, such as the default method for the objects, reference factor, and set of dates.
To period
You use this parameter to determine the date up to which actual values are calculated. The system always calculates plan values for the whole of the period between the planned start date and the planned finish date.
You can specify an exact date instead of a period. To do this, choose
. However, the system only takes account of the date for measurement methods defined on the basis of the "time proportionality" technique.
Select the process control fields you require:
Choose
.
The system selects the objects which satisfy the criteria specified and determines which measurement method is valid. For each object, the system then determines the planned and actual POC in the following configurations:
Aggregated
Not aggregated
For Results Analysis
For more information on the POC, see Progress Calculation .
The system records the POCs determined for the various uses under the statistical key figures defined in Customizing.
For more information, see the Implementation Guide of the
Project System
under
.
The system takes the POC as the basis for calculating the planned and actual earned value (EV).
EV = POC x overall costs
The system records both the original values and the adjusted actual values.
For more information, go to the Implementation Guide of the
Project System
and choose
.
Note
Correction postings are made only for actual values from preceding periods. Current updated values are always recorded in the current period.
For more information, read Correction Postings .
The system records the calculated values by cost element under the cost elements defined in Customizing.
The system also outputs a two-level log:
The basic list contains the number of objects:
To which a method is assigned
In which the plan/actual method was adopted
In which the standard method was used
To call up the detailed list, select a line and choose
Next list level
. The detailed list contains the objects and the methods assigned to them.
You can evaluate values so determined at any time in the information system.
For more information, see Evaluating Project Progress .