Add New Sub Line Items with Resend

Purpose

This process describes the PIP3A8 Request Purchase Order Change business scenario, in which the Buyer wants to include only the new Sub Line Item(s) (discarding the existing Sub Line Items ) in the purchase order, that has already been sent.

In the PIP3A8 Request Purchase Order Change , the Buyer :

  • Wants to resend the original purchase order with changes in the individual data fields , with the GlobalPurchaseOrderChangeCode as Resend

  • Sends only new Sub Line Item(s) with the Product Line Item

Process Flow

In this process, the RosettaNet Mappings transforms the Product Line and Sub Line Items of the PIP3A8 Request Purchase Order Change message to the appropriate Item and Schedule Line of the CRM IDoc .

For further information, see the OBJECT_TASK section under Identification of Messages .

As per given table, the RosettaNet Mappings are implemented as:

  • GlobalPurchaseOrderChangeCode mapped to OBJECT_TASK at Header level of CRM IDoc

  • GlobalActionCode of Product Line Item mapped to OBJECT_TASK at Item level of CRM IDoc

  • GlobalActionCode of Sub Line Item mapped to OBJECT_TASK at Schedule Line levels of CRM IDoc

  • GlobalActionCode ignored at Product Line Item and Sub Line Item levels. OBJECT_TASK flag is set to I (Insert) at Item and Schedule Line levels.

    RosettaNet

    SAP CRM

    GlobalPurchaseOrderChangeCode = Resend

    Start of the navigation pathHeader Next navigation step OBJECT_TASK = CEnd of the navigation path

    Start of the navigation pathProduct Line Item Next navigation step GlobalActionCodeEnd of the navigation path = Add

    Start of the navigation pathItem Next navigation step OBJECT_TASK = IEnd of the navigation path

    Start of the navigation pathSub Line Item Next navigation step GlobalActionCodeEnd of the navigation path = Add

    Start of the navigation pathSchedule Line (Ordered) Next navigation step OBJECT_TASK = IEnd of the navigation path

Example

Scenario

  • A purchase order exists with Product Lines 10 containing Sub Line

  • The Buyer wants to include new Sub Line 2 to the Product Line 10 and resend the Purchase Order.



Request Purchase Order Change

Request Purchase Order Change

  • The Buyer resends PIP3A8 Request Purchase Order Change with Product Line 10 containing new Sub Line

  • The RosettaNet Mappings transforms the Product Line 10 containing Sub Line 2 of Request Purchase Order Change to Item 10 with Schedule Line 2 (in CRM IDoc ).



Purchase Order Change Confirmation

Purchase Order Change Confirmation

  • The Seller System changes the sales order and resends an IDoc with the newly added Schedule Line 2 in Item 10 containing Ordered and Confirmed Schedule Lines .

  • The RosettaNet Mappings transforms the newly added Schedule Line 2 in Item 10 containing Ordered and Confirmed Schedule Lines to Purchase Order Change Confirmation message. The transformed message contains the confirmed Product Line 10 with Sub Line