Revise Product Line Items with Changes (without Sub Line Items)
Use
This process describes the PIP3A8 Request Purchase Order Change business scenario, in which the Buyer wants to revise existing Product Line Item(s) in the purchase order that has already been sent. In the PIP3A8 Request Purchase Order Change, the Buyer:
-
Wants to send only changes, with the GlobalPurchaseOrderChangeCode as Changes
-
Sends only revised Product Line Item(s)
Process
In this process, the RosettaNet Mappings transforms the Product Line Item of the PIP3A8 Request Purchase Order Change message to the appropriate Item and/or Schedule Line of the CRM IDoc. For further information, see the OBJECT_TASK section under Identification of Messages.
As per given table, the RosettaNet Mappings are implemented as:
-
GlobalPurchaseOrderChangeCode mapped to OBJECT_TASK at Header level of CRM IDoc
-
GlobalActionCode of Product Line Item mapped to OBJECT_TASK at Item and Schedule Line levels of CRM IDoc
|
RosettaNet |
SAP CRM |
|---|---|
|
GlobalPurchaseOrderChangeCode = Changes |
Header: OBJECT_TASK = U |
|
Product Line Item: GlobalActionCode = Revise |
Item: OBJECT_TASK = U |
|
Schedule Line (Ordered): OBJECT_TASK = U |
Example
Scenario
A purchase order exists with Product Lines 10 (with 150 pieces) and 20 (with 350 pieces) and the Buyer wants to revise Product Line 20 from 350 pieces to 300 pieces.
Request Purchase Order Change
-
The Buyer sends PIP3A8 Request Purchase Order Change with revised Product Line 20.
-
The RosettaNet Mappings transforms the Product Line 20 of Request Purchase Order Change to Item 20 with Schedule Line (in CRM IDoc).
Purchase Order Change Confirmation
-
The Seller System changes the sales order and sends an IDoc with the revised Item 20 containing Ordered and Confirmed Schedule Lines.
-
The RosettaNet Mappings transforms the revised Item 20 containing Ordered and Confirmed Schedule Lines to Purchase Order Change Confirmation message. The transformed message contains the confirmed Product Line 20 with Sub Lines.