Process XSteps in Process Order If you have selected a master recipe during order creation that contains XSteps, then you can process the transferred XSteps in the XStep editor.
See also: XSteps (Execution Steps)
If a master recipe has been selected that contains characteristic-based process instructions, edit this in the process instruction overview.
See also: Changing Process Instructions in the Process Instruction Overview
Early Issue of Order Number
As default, it is only possible to generate an XStep tree in a process order once the order in question has been saved. You can also set that an XStep tree is generated, even if it has not yet been saved.
To do this, access the Customizing for process management and choose
Execution Steps
(XSteps)
->
Set Early Issue of Order Number
.
You access the XStep editor (
XSteps).
The process order already contains the XSteps that you have defined in the master recipe.
You valuate the XStep parameters that have to be given a fixed valuation, if necessary.
You create new XSteps, if necessary.
You check the XStep trees and correct the any errors that are found.
You simulate and test the PI sheet for individual control recipe destinations.