Executing Collective Availability Checks
Note
This function is not available in Release SAP R/3 4.6. If you require the function, see SAP Note 326591.
You use this procedure to carry out availability checks for several networks at once, to see if all the necessary components are available.
Collective availability checks are executed in the Project Information System from the enhanced individual overview for networks.
Choose .
Enter a PS info profile, if necessary. The initial screen for the information system appears.
Enter the selection criteria and choose
Execute
. You can enter the required networks directly, or select them via projects or WBS elements.
The individual overview for networks appears.
Choose
to select all networks, or expand the structure and use CTRL to select individual networks or SHIFT to select blocks of networks.
Choose .
The
Collective Availability Check
dialog screen appears. The
Reset Availability Data
and
Execute Availability Check
indicators are set as defaults. If you only want to reset the availability data, for example, cancel the second indicator. By choosing
Mode
you go to another window in which you can determine what type of check is carried out and which messages the system should write in the log.
Choose
with the quick info text
Check Availability
.
The system executes the availability check for the selected networks and saves the dates it determines automatically. You can call the log for the availability check by choosing