Activating all Requirements in a HierarchyOn the network header or the activity overview choose
A dialog box appears.
Enter the object for which you want to activate purchase requisitions and reservations:
A network
The system creates purchase requisitions and MRP relevant reservations for all material components and externally processed activities in networks.
A WBS element
The system creates purchase requisitions and MRP relevant reservations for all activities (and the assigned material components) in networks that are assigned to the WBS element.
An activity
The system creates purchase requisitions and MRP relevant reservations for the activity and the assigned material components.
Choose
Continue.
A message appears telling you how many entries were changed.