Assigning Material Components to Standard NetworksChoose
You can also assign material to a standard network when you
create
the standard network.
Enter a standard network and choose
Activitie
s.
Select the required activities in the activity overview and choose
.
Overview
Netwk
.
If no material components have been assigned to the standard network yet, the
Bill of Material
dialog box appears.
If material components have already been assigned to activities of the standard network, a dialog box appears in which the corresponding BOMs are displayed.
If you want to assign further components from a bill of material (BOM) or change the existing assignments, select the BOM.
If you want to assign components from another BOM or create a new standard BOM, choose
Other material
or
Other standard BOM
.
The further procedure is the same as if no components had been assigned.
You assign material components as follows:
If you want to assign components from an existing BOM, enter the material and plant in the dialog box and choose
Continue
.
If several BOM alternatives exist for the material, a dialog box with the alternatives appears. Select an alternative. A list of the material assignments appears.
If no BOM exists for the material, the system asks you, if you want to create a new BOM. If you want to, choose
Yes
, create the BOM and then return to the list of assignments by choosing
Back
.
If you do not want to create a normal BOM, you can use a standard BOM as an aid. For more information, see Creating a Standard Bill of Material for Assigning Material to a Standard Network
Select the BOM items that you want to assign and choose
In the
New Assignment
dialog box, enter an activity or choose
Oper/act. list
to display a list of all the activities. Select an activity from the activity list.
The system assigns the BOM items to the activity.
If necessary repeat the last step to assign further BOM items to other activities.
Choose
Back
.
The activity overview appears again.
Save the standard network.