Assigning Material Components to Standard Networks

  1. Choose Start of the navigation path Logistics or Accounting Next navigation step Project System Next navigation step Basic data Next navigation step Standard templates Next navigation step Standard network Next navigation step Change. End of the navigation path

  2. You can also assign material to a standard network when you create the standard network.

  3. Enter a standard network and choose Activitie s.

  4. Select the required activities in the activity overview and choose Start of the navigation path Activities Next navigation step Component overview Next navigation step or choose Next navigation step Goto Next navigation step Comp End of the navigation path . Overview Netwk .

If no material components have been assigned to the standard network yet, the Bill of Material dialog box appears.

If material components have already been assigned to activities of the standard network, a dialog box appears in which the corresponding BOMs are displayed.

  • If you want to assign further components from a bill of material (BOM) or change the existing assignments, select the BOM.

  • If you want to assign components from another BOM or create a new standard BOM, choose Other material or Other standard BOM .

The further procedure is the same as if no components had been assigned.

  1. You assign material components as follows:

  • If you want to assign components from an existing BOM, enter the material and plant in the dialog box and choose Continue .

If several BOM alternatives exist for the material, a dialog box with the alternatives appears. Select an alternative. A list of the material assignments appears.

  1. Select the BOM items that you want to assign and choose Start of the navigation path Edit Next navigation step New assignment. End of the navigation path

  2. In the New Assignment dialog box, enter an activity or choose Oper/act. list to display a list of all the activities. Select an activity from the activity list.

  3. The system assigns the BOM items to the activity.

  4. If necessary repeat the last step to assign further BOM items to other activities.

  5. Choose Back .

  6. The activity overview appears again.

  7. Save the standard network.