Entering Dates for Several Components

Use

Use this procedure to enter the dates of an event for several components in one step. This could be the case if you have created a common purchase order for several components, for example.

Procedure

  1. Select the column for the event whose dates you want to edit.

  2. Select the relevant components.

  3. Choose Date .

The Set Dates dialog box appears. Here you enter all four date types for the selected event.

  1. Enter the dates, as required.

  2. To copy the dates choose .

Result

The system sets the date for the relevant date types for all the selected components .