Allocating Material Components to Other WBS Elements You use transfer controlto allocate individual material components to another WBS element.
Transfer control has two functions:
You can allocate individual material components to other WBS elements, as described below.
You can define material components as assembly items.
See
Defining Assembly Items for BOM Transfer
Choose
Logistics
or
Choose
Transfer
.
Enter the material and the WBS element to which you want to allocate the material component.
Save your data.
Note
If the component is kept in project stock , the system also changes the stock segment.
If you want the requirements of the corresponding components to be consumed (if they are in project stock), they must both be assigned to the same WBS element, since
requirements consumption
takes place only within the same stock segment and not across projects.