Allocating Material Components to Other WBS Elements

Use

You use transfer controlto allocate individual material components to another WBS element.

Transfer control has two functions:

Procedure

  1. Choose Logistics or Start of the navigation path Accounting Next navigation step Project System Next navigation step Material Next navigation step Planning Next navigation step BOM transfer. End of the navigation path

  2. Choose Transfer .

  3. Enter the material and the WBS element to which you want to allocate the material component.

  4. Save your data.

    Note Note

    If the component is kept in project stock , the system also changes the stock segment.

    If you want the requirements of the corresponding components to be consumed (if they are in project stock), they must both be assigned to the same WBS element, since requirements consumption takes place only within the same stock segment and not across projects.

    End of the note.