Defining Valuation Methods You define valuation methods for the delivered
Valuation Procedure in Line With German Commercial Code and IAS
. These valuation procedures are based on valuation method 09 of the
Results Analysis.
Caution
You must configure exactly the same basic settings as described below in
Procedure
.
In Customizing for
Project System
under
Create a new valuation method.
Enter the controlling area, the results analysis version and the results analysis key.
Note
For both valuation procedures use the same results analysis key.
Specify results analysis method 09 .
Note
The valuation procedure in line with the German Commercial Code and the IAS is based on valuation method 09 of the
Results Analysis.
With this method only a few key figures are transferred during valuation. This method is needed above all for reading the input data.
Save your input.
Select
Expert Mode
.
Note
To configure the valuation method for the valuation of semi-finished constructions, you must also set different key figures. It is only possible to set these key figures in expert mode.
Highlight the items with RELEASED status.
Choose
with the quick info
Detail
.
Change the following key figures for status RELEASED:
Field |
Input |
Description |
|---|---|---|
Valuation basis |
O (not: 0) |
The valuation basis determines how the planning data is calculated. O means planning data for
|
Project structure |
T |
The project structure key figure determines how the data for individual WBS elements is handled in the results analysis. |
Commitment |
G |
Commitment G means down payment should be read for the results analysis. The read down payments can be changed using BAdI /SAPPCE/PNV03. For more information, see SAP Enhancements . |
Final key figure |
D |
D means that for a valuation run only data relevant to the results analysis period is updated. Valuation data already updated from an earlier valuation run is deleted. |
Plan version |
0 |
If necessary enter another plan version, from which the remaining plan and the potential individual risks are read. |
Select the next entry and change the following key figures for RLSD status:
Field |
Input |
Description |
|---|---|---|
Valuation basis |
O (not: 0) |
Planning data from
|
Project structure |
T |
Project structure key figure |
Final key figure |
D |
Data is only updated up until the results analysis period. Valuation data already updated from an earlier valuation run is deleted. |
Plan data is not longer relevant here.
Save your input.