Equal Efforts When Staffing with Multiple Resources
This feature ensures that when a role is staffed with multiple resources at the same time on the cross-project Staffing Overview, equal shares of the required effort are assigned to all resources by default. If the availability of a resource is insufficient to provide its share of the required effort, the remaining demand is divided evenly among the other resources.
Alternatively, you can define your own logic to divide the effort among the resources involved.
If this feature is not active, the system covers the role demand by using up the entire availability of the first resource before consuming that of the second one, and so on.
Technical Details
|
Product Feature Is |
New |
|---|---|
|
Country Dependency |
Valid for all countries |
| Software Component Version |
EPPM 100 |
|
Application Component |
PPM-PFM (Portfolio Management) |
|
Availability |
SAP Portfolio and Project Management 1.0 for SAP S/4HANA (SP03) |
Effects on Customizing
-
To activate this feature, make the following setting in Customizing for SAP Portfolio and Project Management under :
Area Setting Name Description
Setting Value
0011
0014
Equal Effort Assignment When Staffing with Multiple Resources
X -
To define your own logic for effort assignment, implement one of the following methods in Customizing for SAP Portfolio and Project Management under :
-
Method CHANGE_BUPA_DIST for distributed roles
-
Method CHANGE_BUPA_LINKS for roles without distribution
-