Planning and Publishing a Manufacturing Bills of Material

The next step in the process of handover is planning a BOM.

Prerequisites

  • You've created a handover for the recipe formulation using Hand Over Recipe Formulation to Bills of Material app from the launchpad.

    For more information, see Creating a Recipe Handover.

  • You are on the Handover From Recipe to BOM Planner page by choosing a handover activity.

Context

When you create a recipe formulation handover, you choose the created handover to navigate to the handover planning page. The app loads the recipe formulation into the Source panel with all the relevant stages, output streams, ingredients, and input streams. By default, the root assembly from the Source panel is loaded into the Target panel. Choose Edit to perform any planning.

From the handover planning page, you can make your selections for planning and transferring ingredients directly to the Target panel.

For more information about the panels, see Panels.

Procedure

  1. Select the ingredients from the Source panel and choose the planning type that you want to use to plan them to the Target panel.
  2. Check the status of the planned ingredients.
    • In the Source panel, all the ingredients have one of the following statuses along with quantity:
      • (Planned)

      • (Unplanned)

      • (Quantity Discrepancy)

      For more information on the statuses, see Planning Statuses.
    • In the Target panel, few ingredients may have the following statuses:

      Option

      Description

      (Quantity Discrepancy)

      If there is quantity mismatch with the Source panel.

      (Yet to be published to SAP S/4HANA system)

      If the components are not synchronized with the SAP S/4HANA System.

  3. Additional Steps
    Choose any of the following to perform in the Target panel:
    • To edit the attributes of BOM, see Step 4.

    • To remove ingredients, see Step 5.

  4. To edit the BOM item attributes of the selected ingredient, choose (Details) in the Target panel.

    You can update the following attributes of the BOM item:

    Details

    Attributes

    Position Number

    The order of the component placed in the BOM from top.

    Sort String

    It allows you to define a custom sorting sequence a component with the BOM.

    Component Quantity

    The numerical amount of ingredient used for the recipe.

    Unit of Measure (UoM)

    It allows you to change the UoM for the components in the target panel.

    Fixed Quantity

    It indicates that the quantity of a component does not depend on the quantity of the assembly produced or the order quantity.

    Net Scrap Indicator

    It specifies whether to ignore the assembly scrap setting in the header material for the component. It is required if you enter Operation scrap.

    Text Details

    Item Text 1 and Item Text 2.

  5. To remove any ingredient from the target BOM structure, choose (Remove components from the target panel) .
  6. Convert a stock item into a non-stock item:
    1. Select the required components from the target panel.
    2. Select (More) and choose Convert to Non-Stock button.
      You can convert a stock item into a non-stock item only if it is not synchronized with the SAP S4HANA.
  7. After you’ve completed planning to the target BOM structure, choose Unlock .
  8. When you've finalized the BOM structure, you can publish it to the ERP system (SAP S/4HANA Cloud Private Edition, SAP S/4HANA, SAP S/4HANA Cloud Public Edition, or SAP ERP), choose Publish to ERP System.