Working With Propose Linking
You use this procedure to maintain the digital thread (cross-reference) linking between the Source and Target nodes. You use the Propose Linking option along with the Load BOM option in the Target panel.
Prerequisites
-
You've created a handover for an EBOM using the Hand Over Engineering Bills of Material (EBOM) app.
For more information, see Creating a Handover.
-
You've loaded the assemblies in both the Source and Target panels.
Context
The following are the scenarios where the target BOM component may not be generated through planning and there won't be an established link between source and target BOM components:
-
When you import BOMs from other external systems.
-
When you add components (manufacturing consumables) independently in the Target and maintain specific properties.
-
When you load BOM with a different context.
The following procedure showcases how to establish the link between the source and target BOM components: