Setting Up Availability ControlIn the budget profile, you define all values required for the budgeting process.
To do so, in Customizing:
For projects, choose
Project System
Õ
Costs
Õ
Budget
Õ
Maintain Budget Profile
.
For internal orders, choose
Controlling
Õ
Internal Orders
Õ
Budgeting and Availability Control
Õ
Maintain Budget Profile
.
For more information, see
Basic Settings for Availability Control in Budget Profile
.
The tolerance limits for the checks during activity control are defined for each transaction group of a budget profile.
To do so, in Customizing:
For internal orders, choose
For projects, choose
Project System
Õ
Costs
Õ
Budget
Õ
Define Tolerance Limits
.
For more information, see
Specifying Tolerance Limits
.
Exempt cost elements are those which are not included during availability control (such as, interest or credits for activities that were provided in a joint venture by one project for a partner project).
To do so, in Customizing:
For projects, choose
Project System
Õ
Costs
Õ
Budget
Õ
Specify Exempt Cost Elements
.
For internal orders, choose